International Waters learning Exchange & Resource Network

3.2 - Start-Up Phase

This section is divided into the main phases of projects:

Following the check-list a brief introduction to each subject is presented. Where of specific relevance to GEF IW project activities these are expanded further in Parts 3 and through the case studies and other relevant material presented in Part 4.

Project Start-up

Key actions that are needed and responsible parties following CEO signature to the project and delegation of authority (Projects/Executing Agencies should obtain confirmation from the GEF Agency prior to incurring any costs that are to be reimbursed) include:

Activity

GEF implementing agency

GEF executing agency

PCU

PSC

Countries

Signature of the ProDoc by all countries

L

X

Recruitment of Project Manager

X

L

X

Recruitment of technical and administrative staff of the PCU

X

L

X

Host country agreements

L

X

Provision (or procurement) of project offices

L

X

Nomination of PSC members by Countries

L

X

X

X

Nomination of national teams

X

L – Lead; X – involved

These activities are taken by the Implementing and Executing Agencies in partnership with the countries and usually prior to the appointment of the PCU.